Data-Driven Project Scheduling for Telecommunication Site Deployment Based on Failure Risk, Energy Performance and Maintenance Constraints

Authors

  • Salar SeyedAhmadi Ph.D. in Telecommunication Engineering (Fields and Waves), Urmia University, Urmia, Iran. Author

Keywords:

Telecommunication site deployment, resource-constrained project scheduling, failure risk, energy performance, maintenance constraints

Abstract

Telecommunication site deployment involves interdependent construction, power installation, radio equipment deployment, testing, and commissioning activities. Conventional project scheduling approaches primarily emphasize activity durations, precedence relationships, and resource availability, while operational failure risk, energy performance, and maintenance constraints are frequently considered separately. This separation can lead to schedules that are feasible from a construction perspective but insufficiently responsive to equipment reliability, energy requirements, and maintenance-related interruptions. This paper develops a methodological framework for integrating these dimensions into data-driven project scheduling for telecommunication site deployment. The proposed framework conceptualizes deployment as a resource-constrained project scheduling problem in which activity durations, failure-related disruption, energy consumption, maintenance availability, and technical precedence relationships jointly influence scheduling decisions. The research adopts a secondary-data-oriented design based on published studies, documented dataset descriptions, and a structured scenario-analysis approach. The framework comprises five components: data preparation, activity and resource modeling, failure-risk characterization, energy and maintenance constraint integration, and multi-objective schedule evaluation. A baseline schedule is conceptually compared with an integrated scheduling alternative, while sensitivity analysis is specified to examine the influence of failure probability and repair duration on expected disruption. Because the underlying raw datasets were not independently obtained and an integrated optimization algorithm was not executed and empirically validated, the numerical scenarios are illustrative rather than observed findings. Consequently, no empirical reduction in project duration, energy consumption, or failure-related delay is claimed. The principal contribution is a transparent methodological structure for coordinating project scheduling with reliability and energy considerations in telecommunication deployment. The framework provides a foundation for future empirical implementation using verified site-level project records, equipment failure histories, energy measurements, and maintenance logs. Its practical value will depend on data quality, constraint calibration, and validation against actual deployment projects.

References

Asiedu EM, Mkansi M. A comprehensive assessment of time overruns in Ghanaian telecom cell site construction. Cogent Engineering. 2022;9(1):2109250. doi:10.1080/23311916.2022.2109250.

Malafronte L, Sorrentino M, Trifirò A. Development and experimental verification of data-driven approaches to real-time energy monitoring and diagnosis of telecommunication sites. International Journal of Energy Research. 2021;45(10). doi:10.1002/er.6789.

Nastro F, Sorrentino M, Trifirò A. A machine learning approach based on neural networks for energy diagnosis of telecommunication sites. Energy. 2022;245:123266. doi:10.1016/j.energy.2022.123266.

Fu F, Liu Q, Yu G. Robustifying the resource-constrained project scheduling against uncertain durations. Expert Systems with Applications. 2024;238:122002. doi:10.1016/j.eswa.2023.122002.

Wu T, Wang Y, Ye ZS, Chen N. Spatio-temporal analysis and prediction of mass telecommunication base station failure events. Technometrics. 2024;66(1):77–89. doi:10.1080/00401706.2023.2231491.

Li YF, Zhao W, Zhang C, Ye J, He H. A study on the prediction of service reliability of wireless telecommunication system via distribution regression. Reliability Engineering & System Safety. 2024;250:110291. doi:10.1016/j.ress.2024.110291.

Valencia A, Gorbatov O, Eleftheriadis L. Hardware alarms reduction in radio base stations by forecasting power supply units headroom. Electric Power Systems Research. 2022;213:108519. doi:10.1016/j.epsr.2022.108519.

Hartmann S, Briskorn D. An updated survey of variants and extensions of the resource-constrained project scheduling problem. European Journal of Operational Research. 2022;297(1):1–14. doi:10.1016/j.ejor.2021.05.004.

Shahabi-Shahmiri R, Tavakkoli-Moghaddam R, Dolgui A, Mirnezami SA, Ghasemi M, Ahmadi M. Preemptive and non-preemptive multi-skill multi-mode resource-constrained project scheduling problems considering sustainability and energy consumption: a comprehensive mathematical model. Journal of Environmental Management. 2024;367:121986. doi:10.1016/j.jenvman.2024.121986.

Peng W, Yu D, Xie F. Multi-mode resource-constrained project scheduling problem with multiple shifts and dynamic energy prices. International Journal of Production Research. 2025;63(7):2483–2506. doi:10.1080/00207543.2024.2403774.

HUAWEI NETOP Team. 5G Network Energy Consumption Dataset [dataset]. Hugging Face. Dataset access subject to the provider's terms.

Ayala-Romero J, Garcia-Saavedra A, Costa-Perez X, Iosifidis G. Bayesian Online Learning for Energy-Aware Resource Orchestration in Virtualized RANs—Dataset [dataset]. Zenodo; 2021. doi:10.5281/zenodo.6258750.

Sultan RA, Hamdy K, Essawy YAS. Agent-based simulation for multi-resource-constrained scheduling of scattered atypical repetitive projects. Scientific Reports. 2026;16:11759. doi:10.1038/s41598-026-42832-1.

Downloads

Published

2025-04-18

Issue

Section

Research article

How to Cite

Data-Driven Project Scheduling for Telecommunication Site Deployment Based on Failure Risk, Energy Performance and Maintenance Constraints. (2025). Scientific Journal of Research Studies in Future Electrical Engineering, 3(1), 1-9. http://journalhi.com/pow/article/view/474

Similar Articles

You may also start an advanced similarity search for this article.